Plutonic Power Issues Progress Update, First Quarter Ended March 31, 2010 Financial Results - CNW
    Publisher: CNW Group
    Author: Plutonic Power

 VANCOUVER, May 13 /CNW/ - Plutonic Power Corporation (the "Company") (PCC: TSX) announced today a progress update and its financial results in Canadian Dollars for the first quarter ended March 31, 2010.

<<

OVERVIEW

--------

>>

During the first quarter of 2010, construction continued on a timely basis at the East Toba River and Montrose Creek Project ("Toba Montrose"). Construction commenced at the Dokie Wind Project as did the commencement of transportation of the wind towers and turbine equipment to site. In addition, the Company and GE Energy Financial Services ("GE") were offered a 40 year Electricity Purchase Agreement ("EPA") for the 124 MW Upper Toba Project. This EPA was executed with BC Hydro in April.

<<

TOBA MONTROSE UPDATE

--------------------

>>

Toba Montrose is being built with our partner GE through the Toba Montrose General Partnership ("TMGP") in conjunction with our First Nations partners, the Klahoose, Sliammon and Sechelt First Nations, and is fully financed, on- budget and on-schedule to reach commercial operation during 2010. All the electricity to be generated from Toba Montrose will be sold to BC Hydro under a 35 year EPA

Milestones during the first quarter of 2010 include:

<<

- 93% completion of the engineering, procurement and construction

("EPC") contract

- Completed work includes the transmission line, East Toba

powerhouse, penstock and intake

- Ongoing work includes commissioning of East Toba plant, and

completion of Montrose powerhouse, penstock and intake

>>

The transmission line from the Toba Montrose Project is expected to be energized in May for commissioning and testing of electrical components related to the project. Original construction schedules called for commercial operation of East Toba for July, and Montrose Creek in November 2010.

<<

DOKIE WIND PROJECT UPDATE

-------------------------

>>

During the fourth quarter of 2009, the Company and GE formed Dokie General Partnership ("DGP"), to acquire, finance, complete the construction of and operate the 144 megawatt ("MW") Dokie Wind Project in conjunction with our First Nations partners, the Halfway River, West Moberly and Saulteau First Nations and McLeod Lake Indian Band. DGP acquired the partially completed and fully permitted Dokie Wind Project from EarthFirst Canada Inc. DGP arranged debt financing of $175 million and the Company and GE contributed $52.5 million of project equity to finance the completion of the Dokie Wind Project. The Dokie Wind Project is located 1,100 kilometres northeast of Vancouver, near Chetwynd, BC and it will use 48 3-MW wind turbines to generate approximately 333 gigawatt hours ("GWh") of electricity annually net of transmission line losses. Completion of construction and commencement of electricity sales to BC Hydro is scheduled for early 2011 under a 25 year EPA.

Mortenson Canada Corporation ("Mortenson") mobilized to site early January to commence the balance of construction on the Dokie Wind Project. As of March 31, subcontractors were active on all unfinished turbine site locations. Deliveries of the remaining 40 turbines are in progress to a lay down area in Chetwynd. All site roads are complete and Mortenson commenced pouring of concrete foundations in mid-April. Support from the community has been very positive.

<<

2010 UPDATES AND FORECASTS

--------------------------

>>

For the remainder of 2010, in addition to commencing commercial operations at Toba Montrose and commencing the commissioning processes at the Dokie Wind Project, Plutonic will continue to have a very busy year. Upper Toba goals to be completed by year end are: to obtain construction permits, licenses and authorizations; commence project financing discussions; select and engage a contractor; conclude an agreement with the Klahoose First Nation and enter into a formal partnership agreement with GE.

As well, an evaluation on the 156 MW Dokie Expansion Project is underway. Once completed and if deemed feasible, Plutonic and GE would seek to obtain an EPA with BC Hydro, obtain construction permits, licenses and authorizations, seek project financing, select and engage a contractor, and finalize First Nations agreements and enter into a formal partnership agreement with GE.

<<

FINANCIAL RESULTS

-----------------

>>

For the first quarter ended March 31, 2010, the Company incurred a net loss of $2.1 million ($0.03 net loss per common share) compared with a net loss of $11.3 million ($0.26 net loss per common share) for the quarter ended March 31, 2009. The Company's net loss for the quarter ended March 31, 2010 is comprised of $2.1 million (March 31, 2009 - $2.1 million) in net cash operating expenditures, and $28,929 in net non-cash operating gains (March 31, 2009 - $9. 2 million loss), including share based compensation, share based guarantee fees, and an unrealized gain on the fair value adjustment of interest rate swaps.

As at March 31, 2010, the Company had $10.6 million in consolidated cash, $44.6 million in consolidated cash restricted to construction and consolidated working capital of $43.7 million. Excluding its respective proportionate 40% share of TMGP cash and working capital and 51% share of DGP cash and working capital as at March 31, 2010, the Company had $7.9 million in cash and $10.9 million in working capital.

As at March 31, 2010, the Company had recorded $253.4 million in long term debt, $293.4 million in property plant and equipment and $5.8 million in intangible assets, based on its 40% share in TMGP and 51% share in DGP. The long term debt of TMGP and DGP are secured by the assets of TMGP and DGP respectively and are non-recourse to the other assets of the Company.

This financial summary should be read in conjunction with the Company's March 31, 2010 unaudited interim consolidated financial statements and Management's Discussion and Analysis, both of which are available on www.sedar. com and on the Plutonic Power Corporation web site at (www.plutonic.ca») FinancialReports.asp
 
 

You can view the Previous Media Coverage item: Sat May 15, 2010, Dry winter to blame for BC Hydro decision to boost energy imports - Vancouver Sun

You can view the Next Media Coverage item: Tue May 4, 2010, Out of disaster, an awakening - Ottawa Citizen

You can return to the main Media Coverage page, or press the Back button on your browser.

Suite 600 : 888 Dunsmuir Street : Vancouver, BC : Canada : V6C 3K4