Photos



Feedback Form
Previous. All pages. Next. Page 1. Page 2. Page 3in  columns

A foundation site ready for the 26 concrete truck loads that will deliver a continuous pour

A view down on a tower foundation under construction

A view to wind turbines JC-1, JC-9 and JC-15 on a late winter day

A worker climbing a ladder in the 80 metre tower

An anchor bolt assembly for a tower base is being prepared to be lifted into place

Bolts of the anchor bolt assembly connect the foundation to the first tower section

Building the forms in preparation for the concrete pour

Components, such as these Nacelles and tower sections, continue to arrive by rail in Chetwynd and are stored in the CanFor yard

Foundation mud mat with the first course of the footing rebar in place

JC-1 Turbine at Dokie

Local contractor, Chetwynd RediMix, has their concrete batch plant up and running on site

Pumping concrete for the "mud mat", the first step in construction of the tower foundation

Reinforcing steel in the tower foundation

The anchor bolt assembly of the tower base incorporated in the foundation rebar

The freshly poured concrete is covered to aid in the cure process. The combined weight of the steel and concrete in a tower foundation is 650 tonnes

The view from the top of a nacelle

Assembly of the steel frame of the powerhouse building

Assembly of the steel frame of the powerhouse building

Cabling on top of a generator

Cutting torch used on the penstock

Fitting a panel of the Coanda screen on the intake

Fitting generator bed plates in the powerhouse

Generator in place

Inside the powerhouse

Installing a generator top bracket

Intake

Intake from across the headpond

Intake looking upstream

It's a thumbs up for energization of the transmission line and substation

Looking down the transmission line to the substation at Saltery bay

Looking downhill over the backfilled penstock to the powerhouse

Looking downhill to the powerhouse site

Looking downstream to the intake

Looking upstream over the intake

Mounting generator top bracket

Mounting pelton wheel to the underside of the generator

One of the six flow nozzles per generator that directs water on to the pelton wheel

Pelton wheel

Penstock complete

placing Bentolite liner on the headpond banks

Placing the headpond liner on the upstream side of the intake

Powerhouse and switchyard

Powerhouse and switchyard. The powerhouse is comparable in size to an average high school gymnasium.

Preparing for a pelton wheel installation

Ready for the last piece of nearly 5 km of penstock

rip-rap placement at the intake

Saltery Bay substation

Switchyard components being installed

The master control console

The process of backfilling and compacting the penstock continues

Aerial view of the East Toba intake structure. (1)

Aerial view of the East Toba intake structure. (2)

Aerial view over the Montrose intake structure, looking down the valley. Water flows through the temporary diversion to the right in the photo.

Aerial view over the Montrose intake structure.

Aerial view over the Montrose intake structure. Looking upstream.

An aerial view over the East Toba Powerhouse and up the penstock alignment.

Concrete formwork in place at the Montrose intake structure.

Crews connecting ends of the conductor cable on the transmission line. (1)

Crews connecting ends of the conductor cable on the transmission line. (2)

East Toba powerhouse with backfill nearly complete. The mouth of the tailrace can be seen centre-front of the photo.

Head gate portal and transition structure to the penstock at the East Toba intake.

Inside, looking out through the transition structure.

Looking down the penstock to the East Toba powerhouse.

More rebar is swung on to the floor platform by crane and positioned by a Kiewit worker.

Positioning a penstock connection for welding.

Progress over the past few months on the East Toba powerhouse.

Rebar and channel ties ready for an abutting concrete wall to be formed and poured.

Rebar being tied within the powerhouse floor slab.

Rebar on the spillway at the East Toba intake.

Tack welding guides to the penstock in preparation for the next pipe section.

The concrete walls from the bottom of the spillway collector channel.

View from the East Toba Powerhouse up the penstock alignment.

A welder at the mouth of the penstock.

A worker ties some of the miles of re-bar.

Al and Gilbert of the Klahoose First Nation, hired by Plutonic Power for fieldwork in Summer 2005

All workers on site wear regulated safety equipment at all times, including high visibility vests, eye protection, gloves, CSA approved steel toe boots, long sleeves and pants.

And Still More Rebar

At top of photo, a riparian repair of old logging damage is visible. The upgraded, historic forestry road parallels the transmission line right-of-way which was cleared less than two years ago. The ROW is greening up well.

Barge at Low Tide

Barge Loading

Barge Loading

Barge Loading

Barge Loading

Barge Loading

Barge to Toba

Barge Towing

BC Hydro 2006 Call for Power Press Conference

BC Hydro 2006 Call for Power Press Conference

BC Hydro 2006 Call for Power Press Conference

Biurcation (green) and penstock (yellow) sections are carefully aligned by the crane operators for welding.

Bridge 1 Demo

Bridge container

Bridge Decks

Bruce Ripley presents at BC Chamber of Commerce Energy Summit

Careful planning of the transmission corridor allowed us to use existing logging access roads and pass through existing logging cuts. You can see a continuation of our transmission corridor cresting the ridge.

Chief Duane Hansen - Klahoose First Nation

Chief Duane Hanson and Bob Poore - Plutonic Power

Chief Duane Hanson and Bob Poore - Plutonic Power

Chief Duane Hanson and Donald McInnes - Klahoose Signing Ceremony March 2007
Previous. All pages. Next. Page 1. Page 2. Page 3in  columns
 © 2010 Plutonic Power Corporation. All rights reserved. All material used and displayed on this website, including but not limited to photographs, videos, text, graphics and images ("Content") is the property of Plutonic Power Corporation or its suppliers. All Content is protected under Canadian and international copyright laws and treaties. You may temporarily download Content for personal transitory viewing, provided that: (a) use of the Content is for informational and non-commercial personal use only and no Content may be copied or posted on any network computer, used for public display or broadcast in any media, and (b) no modification of any Content is made. The reproduction, distribution, performance, display, retransmission, broadcast, modification, dissemination, and any use other than non-commercial, non-public personal use, of any Content is expressly prohibited without the prior written permission of Plutonic Power Corporation. To inquire about the use of any Content on this website, please contact us @ 604-669-4999 or info@plutonic.ca.
Suite 600 : 888 Dunsmuir Street : Vancouver, BC : Canada : V6C 3K4